How to fund a big contract in NZ: work out the cash gap before the first payment lands

Winning the job is the easy part. Materials and wages go out weekly; the first progress payment can be a month or more away. Here's how to size the gap, handle the GST, and cover it.

Updated 26 November 2026 · The Business of Money editorial team (NZ)

See if you qualify →No credit check to enquire
Stacked timber and exposed roof framing inside a building under construction, the materials a contractor pays for before the first progress claim is paid

Quick answer

To fund a big contract in New Zealand, work out your cash gap first: total the weekly wages, materials and subcontractor costs, then subtract what the customer actually pays and when. With progress claims and 20-working-day payment timing, the peak gap can be more than half of the job's direct costs, as the worked example shows. Cover it with deposits, tighter supplier terms and, where that isn't enough, working capital arranged before the job starts.

Ready when you are

Check your options in about 60 seconds

A few quick questions. Asking won't touch your credit file, your details aren't sent to a pile of lenders, and a real person reads every enquiry.

Key points

  • The gap peaks just before a progress payment arrives, not at the end of the job.
  • Under the Construction Contracts Act, payment is due 20 working days after a valid claim unless your contract says otherwise, so a claim made today can be a month away in cash.
  • Each progress payment is its own supply for GST. On the invoice basis you can owe GST before the customer has paid you.
  • Retention held by the customer is cash you have earned but can't spend until later; allow for it in the forecast.
  • Arrange funding before the contract starts, while the forecast looks strong, not the week payroll doesn't balance.

You can fund a big contract by finding the cash gap first: the most money you’ll be out of pocket between paying for materials and wages and being paid. Cover it with deposits, supplier terms and, if those fall short, working capital arranged before the job starts. If you’ve already won the work and the numbers worry you, check where you stand now and read on while you do.

The gap is rarely where owners expect. It isn’t at the start, when little has been spent, or at the end, when payments have caught up. It peaks in the middle, in the days before a progress payment lands. The rest of this feature shows how to size it.

How big is the cash gap on a contract?

The gap is cumulative costs paid out minus cumulative payments received, at its worst point. Plot it week by week and the peak usually sits just before a progress payment arrives, because that is when you’ve paid the most and been repaid the least.

An illustrative example, with made-up figures: a Hamilton builder wins a $240,000 (GST-exclusive) fit-out over 12 weeks, claiming $80,000 at the end of weeks 4, 8 and 12. Direct costs are 70% of the price, or $168,000: $14,000 a week for labour, materials and subcontractors.

Week Costs paid out (cumulative) Payments received (cumulative) Gap
4 (claim 1 sent) $56,000 $0 $56,000
8 (claim 1 paid, claim 2 sent) $112,000 $80,000 $32,000
12 (before claim 2 is paid) $168,000 $80,000 $88,000
12 (after claim 2 is paid) $168,000 $160,000 $8,000

The peak is $88,000, about 37% of the contract price and 52% of the direct costs, even though the job is profitable and the customer pays on time. This assumes each claim is paid four weeks (20 working days) after it’s sent. If the customer pays a week late, the $88,000 simply stays out a week longer, and on a longer job where costs keep running, a late payment makes the peak itself higher.

When will the customer actually pay?

For construction work, the Construction Contracts Act 2002 sets the default: a valid payment claim falls due 20 working days after it’s made unless the contract says otherwise. A customer who disputes the amount has to respond with a payment schedule within the contract timeframe, or 20 working days if the contract is silent, and the Act lets a contractor give notice and suspend work for unpaid amounts.

So a claim sent on a Friday is, in practice, cash about a month later. Two lessons follow:

  • Claim on time and claim in the right form. Late or poorly drafted claims push your cash out further. MBIE’s guide to the Act is the place to check the process.
  • Don’t assume the 20th-of-the-month rule. Outside construction work, large customers often pay on the 20th of the month after invoice, which can be anywhere from 20 to 50 days. Our page on 20th-of-the-month payment terms shows how to read your own terms.

If your contract isn’t construction work, your payment terms are whatever you negotiated, so the first job is to read them.

What does GST do to the cash on progress claims?

On a progress claim, GST can leave your account before the customer’s payment arrives. Inland Revenue treats each progress payment as a separate supply, and the time of supply is the earlier of the payment being made or an invoice being issued, per its special supplies guidance.

What that means for you depends on your accounting basis:

  • Invoice or hybrid basis: you account for GST in the return for the period the claim is invoiced, due or paid, whichever is earliest. In the example, claim 1 carries $12,000 of GST. If your return falls due before the customer pays, you fund that GST from your own pocket.
  • Payments basis: you account for GST when the money arrives, so the timing gap doesn’t hit. The eligibility test is on Inland Revenue’s accounting basis page, and our GST accounting basis page explains the trade-offs.
  • Deposits count too. Once you receive a deposit under a contract, the time-of-supply rule is triggered, so set the GST aside straight away.

On the other side, input GST on materials is claimed under the same basis rules. The GST and provisional tax planner helps you see the net effect month by month.

What about retention?

Retention is cash you’ve earned but can’t touch. If your contract holds back, say, 5% of each payment, that is $4,000 of every $80,000 claim, or $12,000 over the job, released later. Under commercial construction contracts, retention must be held on trust, and since the 2023 amendment (in force from 5 October 2023) there are offences and penalties for failing to do so. See Building Performance’s retention page.

For your forecast the rule is simple: treat retention as not yet received. It raises the gap in the final weeks, and you’ll need to carry it through to release.

How do you shrink the gap before borrowing?

Shrink the gap first and borrow for what remains. Each lever below moves the peak in the example table:

  1. Front-load the claims. A deposit or a larger first claim brings payments forward. A deposit received before work starts lowers every figure in the gap column by the amount of the deposit, until later claims offset it.
  2. Claim more often. Fortnightly instead of four-weekly claims cut how much work sits unpaid.
  3. Stretch supplier terms. Terms on the 20th of the following month for materials push big bills past the peak. Our stock and supplier terms page covers how to ask.
  4. Stage the buying. Order materials as each stage starts rather than in one hit.
  5. Price the cost of capital in. If the job needs funding, put the funding cost in the quote. Your break-even point shows how much margin you have to spare.
  6. Check your reserve. If your cash reserve covers the remaining gap with a buffer, you may not need to borrow at all.

How do you cover what’s left?

Match the funding to the shape of the gap. A gap that opens when you start and closes when the claims are paid is a working capital need, and it should be repaid from the contract’s receipts.

Gap type Usually suits
Materials and wages before progress payments Working capital sized to the peak, drawn as needed
Plant or equipment bought for the job Term funding over the equipment’s working life
Retention held after the job Short-term funding or a reserve, repaid on release
A very large contract, with property available Property-secured funding, from $20,000 to $5,000,000

We look at unsecured options for trading businesses, typically $5,000 to $500,000 and sized on turnover and bank statements. What you can get depends on your trading history and numbers, so there’s no promise either way. Our growth plan funding page covers how to test whether a plan pays for its funding, and why growth eats cash explains the pattern in general.

What happens when you enquire, and what should you have ready?

Enquiring takes about 60 seconds. A person on the team reads it and calls you to talk through the contract and the gap. To make the first call useful, have these to hand:

  • The contract value, start date and payment terms (claims, due dates, retention).
  • Your own estimate of the peak gap and when it falls.
  • A recent bank statement and your latest GST return.
  • Who the customer is and whether you’ve worked with them before.

Don’t wait until the job is under way. Lenders can only size an option when your numbers look healthy, and enquiring earlier gives you more choice.

Won a big job? Let’s make sure you can afford to do it

A contract that needs more cash than you have is a good problem, but it’s still a problem. If your forecast shows a gap you can’t comfortably carry, see if you qualify before materials are ordered. Enquiring takes about a minute and won’t touch your credit file. Your details aren’t sent to a pile of lenders, so your phone won’t light up, and a real person reads your situation and calls you. Please fill in the form accurately, including the contract value and when payments fall due, so we can match the right option first time.

Owe suppliers before the first claim is paid? See what could land in time →

Frequently asked questions

How much cash does a big contract tie up before I'm paid?

It depends on how you're paid, but a useful rule is to total every cost you'll pay out before the first and second payments arrive. On monthly claims paid 20 working days later, that is often two to three months of costs. The worked example below shows a $240,000 job peaking at about $88,000 out of pocket.

When does the customer have to pay a progress claim?

For construction work covered by the Construction Contracts Act 2002, the default is 20 working days after a valid payment claim if the contract doesn't set a date. A payer who disagrees generally has to respond with a payment schedule within the contract timeframe, or 20 working days if the contract is silent. Check your own contract and the Act.

Do I pay GST on a progress claim before I'm paid?

On the invoice or hybrid basis, yes in many cases. Inland Revenue treats each progress payment as a separate supply, and the time of supply is the earlier of payment or invoice. On the payments basis you account for GST when you receive the payment. See our GST accounting basis page.

Can I ask a customer for a deposit or earlier progress payments?

Yes, and it is the cheapest way to shrink the gap. A deposit or a front-loaded first claim cuts the amount you need to fund. Remember a deposit is a supply for GST purposes once received under a contract, so set the GST aside.

What is retention money and how does it affect cash flow?

Retention is a percentage of each payment the customer holds back until the job or defects period is finished. Under commercial construction contracts it must be held on trust. It is your money, but you can't use it until released, so leave it out of the cash you plan to spend.

How early should I talk to a funder about a contract?

Before you sign, or at least before materials are ordered. A lender looks at trading history, turnover and bank statements, so a business that enquires while the books look healthy has more choice than one that asks mid-job.

Numbers done? Let's talk about funding them

About a minute to tell us the amount and the reason. No credit check to ask, no passing your details around, and a person on our NZ team who rings you with options that suit.

No credit check to ask

Not shopped around

A person, not a portal